1. Possess the professional technology of mechanical and electrical equipment installation, intermediate title or above, registered mechanical and electrical engineering construction engineer, more than five years of project management experience; 2. Sign a formal contract with the company for more than 5 years of housing subsidies of 1 million.
Service Hotline
13377131018
Guangxi's first smart port shore power system put into operation
Release Time:
2019-11-21 16:02
Source:
On December 28, 2016, Guangxi Fangchenggang Ship Shore Power Project was officially launched, marking the commissioning of Guangxi's first intelligent port shore power system. For the first time, ships docked at the dock have realized the replacement of auxiliary engine fuel power supply with shore power. The project not only saves costs for docked ships, but also realizes energy saving and emission reduction while implementing electric energy substitution, which will bring good economic and social benefits.
Fangchenggang is the largest port in western my country. With the sustained and rapid economic development, the number of ships docked at Fangchenggang has increased significantly in recent years, accounting for 70% of the throughput of coastal ports in Guangxi. The fuel power supply of ships is affected by the quality, scale and quality of the ship's own equipment. The fuel oil utilization rate is not high and the loss is serious, resulting in a lot of waste and affecting the port city environment.
In the past, in order to meet some of the loading and unloading operations and the electricity demand for production and living on the ship, the auxiliary fuel-fired generator on the ship needed to work 24 hours a day when the ship docked at the port. Now with the smart shore power box, the power grid supplies power to the electrical equipment on board, and the cost of using shore power per hour is only about 1 yuan. "This set of shore power supply can safely, reliably and efficiently deliver shore power to ships docked at the wharf. Compared with the previous diesel generators, it is more convenient and safe to generate electricity, and the reliability of power supply is also higher." Director of the Marketing Department of Fangchenggang Power Supply Bureau of Guangxi Power Grid Corporation Yang Yixiong introduced.
After the current shore power project is put into operation, it is expected to increase the power supply by 500,000 kWh every year, replace diesel fuel combustion by 196 tons, and reduce carbon dioxide emissions by 621 tons. It has good environmental protection and economic benefits. Green shipping" plays an important role.
Since 2016, China Southern Power Grid Corporation and Guangxi Power Grid Corporation have made every effort to promote "replacing coal with electricity" and "replacing oil with electricity".
During the construction of the shore power project, South Grid Energy Company and Fangchenggang Power Supply Bureau gave full play to their industry advantages to provide customers with "one-to-one" exclusive services of key account managers, and to install power supply cables, distribution boxes and metering devices for shore power. Provide on-site technical guidance for other work; assist customers to do electricity load forecasting and analysis, help customers determine reasonable power supply plans and equipment parameters, and open up green channels for customers to increase electricity capacity.
In late December 2016, Fangchenggang Shore Power Project was successfully completed. A total of 4 berths have been built on the wharf of Fangcheng Port Authority, and a shore-based power supply operation platform for port ships has been built. It is equipped with 8 sets of 200 kVA low-voltage shore power boxes with a total capacity of 1.6 MW, which can supply electricity for 8 ships at the same time.